|
Preliminary
Engineering Report & Cost Estimates
FY 2007 CWSRF Loan Program for City of
Huntsville
Sanitary Sewer Evaluation
Surveys for Spring Branch, Aldridge Creek, and Big Cove
Service Basins - Phase II
Project will consist of conducting Flow Isolations,
Smoke Testing, Manhole Inspections, and Wet Weather
Testing. Project will identify areas that
contribute to Inflow/Infiltration.
Probable Cost Estimate: $300,000
Large Diameter Line Cleaning
for Spring Branch and Aldridge Creek Sanitary Sewer Basins.
Project will consist of cleaning all Large Diameter
Sanitary Sewer Interceptors (24" to 48").
Approximately 125,000 LF of Sanitary Sewer Interceptors
will be cleaned within the project.
Probable Cost Estimate: $700,000
Sewer Rehabilitation in
Aldridge Creek Service Basin - Phase II (Project 1, 2,
& 3)
Project will consist of performing sewer
rehabilitation within the Aldridge Creek Service Basin
as identified by SSES reports. Methods of
rehabilitation will include pipe bursting, cure-in-place
pipe lining, manhole rehabilitation, and total sewer
replacement. Method of sewer rehabilitation will
vary depending on results and recommendations from the
SSES performed under the 2006 SRF Loan.
Probable Cost Estimate: $1,000,000
Sewer Rehabilitation in
Spring Branch Service Basin - Phase II (Project 1, 2,
& 3)
Project will consist of performing sewer
rehabilitation within the Aldridge Creek Service Basin
as identified by SSES reports. Methods of
rehabilitation will include pipe bursting, cure-in-place
pipe lining, manhole rehabilitation, and total sewer
replacement. Method of sewer rehabilitation will
vary depending on results and recommendations from the
SSES performed under the 2006 SRF Loan.
Probable Cost Estimate: $1,000,000
Sewer Rehabilitation in Big
Cove Service Basin - Phase II (Project 1, & 2)
Project will consist of performing sewer
rehabilitation within the Big Cove Service Basin as
identified by SSES reports. Methods of
rehabilitation will include pipe bursting, cure-in-place
pipe lining, and manhole rehabilitation. Method of sewer
rehabilitation will vary depending on results and
recommendations from the SSES performed under the 2007
SRF Loan.
Probable Cost Estimate: $1,000,000
FY 2006 CWSRF Loan Program for City of
Huntsville
Pump Station SCADA System
Upgrade
Project to consist of upgrading Pump Station SCADA
system for all pump stations within the collection
system. Project will aide in preventing possible SSO's
by allowing greater response time during pump station
outages and monitoring pump stations performance and
activities.
Probable Cost Estimate: $750,000
Aldridge Creek WWTP
Improvements
Project will provide upgrades to the headworks, the
wastewater RAS/WAS building, additional covered sludge
drying beds for sludge disposal, and various yard piping
modifications.
Probable Cost Estimate: $1,300,000
2 MGD Upgrade to the Big
Cove WWTP
Project will provide upgrades to the headworks, the
addition of a 2 MGD oxidation ditch and final clarifier,
upgrade to disinfection facility, and additional covered
drying beds for sludge disposal.
Probable Cost Estimate: $6,600,000
Permanent Backup Power for
Pump Stations - Phase I
Project will consist of providing permanent backup
power to major pump stations within the collection
system. Phase I shall include the following pump
stations: Bob Wallace, Squaw Valley, and Indian Creek
This project will aide in addressing and preventing SSO
problems due to power outages at pumping stations.
Probable Cost Estimate: $300,000
Chemical Root Control
Application for Spring Branch and Aldridge Creek Sanitary
Sewer Basins
Project will consist of applying chemical root
control to sanitary sewer lines (Approx. 300,000 LF)
within the Spring Branch and Aldridge Creek Sanitary
Basins. Areas within these sanitary sewer basins that
are scheduled for the Chemical Root Control Application
will be based on Department of Water Pollution Control's
Root Database.
Probable Cost Estimate: $2,500,000
Sanitary Sewer Evaluation
Surveys (SSES) for Spring Branch and Aldridge Creek - Phase
I
Project will consist of conducting Flow Isolations,
Smoke Testing, Manhole Inspections, and Wet Weather
Testing. Project will identify areas that contribute to
Inflow/Infiltration. This project will be the basis for
determining specific areas for rehabilitation on Project
#7.
Probable Cost Estimate: $550,000
Sewer Rehabilitation in
Aldridge Creek and Spring Branch Basins
Project will consist of performing sewer
rehabilitation in areas identified by SSES reports.
Methods of rehabilitation shall consist of CIPP lining,
pipe bursting, manhole rehabilitation and/or dig and
replacement of sewer lines. Results from data obtained
in Project #6 of this FY06 loan will determine the
method of rehabilitation.
Probable Cost Estimate: $2,200,000
Squaw Valley Parallel
Interceptor
Project will consist of providing additional capacity
to the existing Spring Branch Sewer Basin by
constructing a parallel sanitary sewer interceptor
(Approx. 4,500 LF).
Probable Cost Estimate: $800,000
Spring Branch WWTP -
Upgrades to Influent Pump Station and Chlorination Facility
Project will consist of providing new influent pumps,
controls, and permanent backup power to the Influent
Pump Station Building. Also new chlorination equipment
will be installed in the existing chlorination building.
Probable Cost Estimate: $1,000,000
|